Gantt start date changes end date too but with 5 minute difference

Hi,
I have problem with ejGantt control. Here is example:
http://jsplayground.syncfusion.com/kta41eme

When you try to change "Start Date" value with date picker (for example to 2016-10-10 08:30), "End Date" will change to value 2016-10-10 16:25, but should change to 2016-10-10 16:30. Can you explain me why? 

1 Reply

SR Suriyaprasanth Ravikumar Syncfusion Team September 12, 2017 01:47 PM UTC

Hi Kamil, 
 
We regret for the inconvenience caused.  
We can able to replicate the reported issue in our sample. Hence, we have logged bug report as “Invalid end date calculated while using duration unit as day and project date as datetime”. The fix for the issue will be include in our upcoming volume 3 SP2 release, it will be expected to out at end of September, 2017.  
In the meantime, you can prevent this issue by setting “durationUnit” property as either “hour” or “minute”.  
Please let us know, if you require any other assistance.  
Regards,  
Suriyaprasanth R 